LAAP is a professional association created in 2001 by the architects Sandro Di Gangi and Antonino Palazzolo. LAAP deals with:
- town planning,
- development of renewable resources,
- environmental analysis and management.
LAAP professional activities are spread mainly trough the praxis of Trustee Assignment (Incarico Fiduciario), Law 109/94 article 17 and trough the partecipation in International Competitions in Architecture and Urban.
LAAP offers a technical support for national and Regional Wildlife Parks, for Local and Provincial Councils. LAAP also offers creative and practical support for research funding instruments, for local development actions, for urban renewal projects, for landscape analysis and interpretation.
LAAP activity in the field of environmental improvement has been taken account by these university departments: Hydraulic
Engineering, Environmental Engineering, Animal Biology, Engineers and Agroforestry ITAF.
LAAP, also, avails itself of constant partnerships with Associations of Environmental Offices: Doc. Biologist Bruno Zava’s “Wilderness” and Doc. Ecologist Giuseppe Filiberto’s GREEN FUTURE-Observatory of industrial and landscape ecology.
Together with the town planning, LAAP deals with VIA Processes (Verification of Environmental Impact), Technical Testings, Technical and Economic Advices, Research and Experimental Studies about the Planning for developing Countries in Eastern Africa.
Particular importance have the experiences in the field of waste disposal and water purification, together with the projects related to photovoltaic and eolian power systems. LAAP follows, in fact, all the phases connected to the production of renewable energy: from the stage of researching suitable lands, to the stage of constraints screening, to the stage of project and site management. |
Development of renewal energies: schedule
Laboratorio di Architetture Aggregazione Palermo
40 photovoltaic systems, in the provinces of:
- Trapani
- Agrigento
- Caltanissetta
- Messina
- Cosenza
2 biomass central in the provinces of:
- Ragusa
- Agrigento
1 wind power plant in the province of Trapani
1 thermodynamic solar plant in the province of Caltanissetta |
 |
Time schedule of a type photovoltaic system development path in Sicily
Laboratorio di Architetture Aggregazione Palermo
PHASE |
TIME |
Research of the suitable lands for the photovoltaic power systems, constraints screening, signature of the contract with the landowners |
1 month |
Request for ENEL electrical connection |
2 months |
Formulation of the S.T.M.D. Minimum Technical Solution Detailed (Soluzione Tecnica Minima di Dettaglio) by ENEL |
Definitive Project, drawn in regard of the obtained ENEL’ STMD e checking for V.I.A. process Valutazione Impatto Ambientale (Verification of Environmental Impact) (art. 20 DLgs 04/2008) |
1 month after receiving S.T.M.D. |
Management and Control of the authorization route until the achievement of Single License (Autorizzazione Unica), Legislative Decree 387/2003, granted by Regional Industry Department inside of a Conferenza di Servizi (Conference of Services) with the involvement of about thirty organizations. |
about 16 months |
|
Tot. about 20 months |
|